19 January 2026 to 1 March 2026

Works are underway in Burwood to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm, Monday to Friday and 7am to 1pm, Saturday

Night works: 6pm to 7am, Monday to Saturday

24 hour works: Monday to Sunday

The following works will be carried out during February.

WhereWhen What we are doing What to expect
Burwood Highway, Burwood24 hour works: From 2 February for up to 8 weeks
  • Moving services
  • Eastbound and westbound lane closures between McIntyre Street and Gillard Street at times
  • Medium to high levels of noise, dust and vibration
  • Pedestrian detours
SRL site compound
24 hour works: Ongoing
  • Site mobilisation
  • Medium to high levels of noise, dust and vibration
  • Light spillage
Sinnott Street, BurwoodDay works: From 2 February for up to 2 weeks
  • Commissioning services
  • Road closures between McComas Grove and Highbury Road
  • Up to 18 car spaces closed
  • Low levels of noise, dust and vibration

Traffic disruptions are subject to change due to conditions outside of our control, please visit Big Build Disruption Map to get the latest available information.

Acoustic sheds

Two out of three acoustic sheds will start taking shape over the coming months. These purpose-built structures will be lined with sound-absorbing panels and are designed to contain noise, dust, and light spill from tunnelling operations.

Burwood day works

Burwood night works

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to community by:

  • Maintaining access to businesses and homes
  • Transporting materials from site in covered trucks to minimise dust
  • Installing road safety and detour signage
  • Positioning light towers away from properties
  • Monitoring noise, dust and vibration levels
  • Using water and dust suppressants.

Sign up for SMS notifications

Thank you for your patience and cooperation as we progress the delivery of SRL East at Burwood.