23 November 2026 to 1 February 2027

Clayton 施工进展

Works are underway in Clayton to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
24 hour works: Monday to Sunday

The following works will be carried out during December 2026 and January 2027.

WhereWhen What we are doing What to expect
SRL worksite, Clayton Road, Clayton

24 hour works: Ongoing

  • Excavating the station site
  • Increased truck and heavy vehicle movements, including oversize deliveries
  • Moderate levels of noise, light, dust and vibration
  • Overnight deliveries at times

Clayton Road, Clayton

Day works: Ongoing 
  • Site maintenance
  • Northbound lane closure between Colonel Street and Dunstan Street

Carinish Road, Clayton

Day works: Ongoing              
  • Drainage and landscaping works
  • Site maintenance
  • 24/7 road closure between Madeleine Road and Link Road from late January for up to 2 weeks
  • Lane and footpath closures at times
  • Bus access maintained
Link Road, Clayton Day works: Ongoing
  • Drainage and landscaping works
  • Site maintenance
  • 24/7 road closure from late January for up to 2 weeks
  • Lane and footpath closures at times
Madeleine Road, Clayton Day works: Ongoing
  • Site maintenance
  • Lane and footpath closures at times

Additional short term traffic changes will be in place around the Clayton area as we complete site investigation works in the area.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction.

The Project supports businesses and residents to continue to live, work, study and shop in their community. Clayton shopping precinct remains open and accessible throughout these works.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

Holiday shutdown

There will be no Suburban Rail Loop works during the holiday period from Wednesday 23 December 2026 to Tuesday 12 January 2027 inclusive at Clayton.

Truck and heavy vehicle movements

There will be increased truck movements in the area as we continue to excavate the future station site, remove soil and deliver large equipment to the Clayton worksite. Soil removed from site will be safely transported to disposal locations in line with project and Environmental Protection Authority requirements.

How we will manage our works

  • Maintaining access for emergency vehicles and buses at all times
  • Maintaining access to homes and businesses
  • Transporting materials from site in covered trucks to minimise dust
  • Using water and dust suppressants
  • Installing road safety and detour signage
  • Pedestrian and cyclist detours in place.