27 June 2025 to 1 August 2025

Clayton 施工进展

Works are underway in Clayton to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday

Extended works: 6pm to 10pm Monday to Saturday

Night works: 6pm to 7am Monday to Sunday

24 hour works: 7am Monday to 7am Sunday

WhereWhen What we are doing What to expect
SRL worksite on Clayton Road, Clayton Day/night/extended works: Ongoing

24 hour works: Mid July until early September
  • Preparing to excavate the station site
  • 24 hour works from mid July until early September
  • Ongoing extended working hours until 10pm
  • Increased truck and heavy equipment movements
  • Intermittent overnight deliveries
  • Moderate levels of noise, dust and vibration

Clayton Road, Clayton

Day/night works: Ongoing
  • Site establishment
  • Overnight road closures between Colonel Street and Carinish Road until early July
  • Long term northbound slow lane closure
  • Long term western footpath closure
  • Intermittent lane closures

Haughton Road east, Clayton

Day/night works: Early to mid July
  • Landscaping
  • Site establishment
  • Intermittent lane and footpath closures
  • Pedestrian detours for up to 4 days
  • Overnight closure of Haughton Road between Clayton Road and Pullyn Street for up to 2 nights
Link Road, Clayton Day/night works: Ongoing until late July
  • Site establishment
  • Intermittent lane closures
Carinish Road, Clayton Night works: Ongoing
  • Moving underground services
  • Site establishment
  • Road closure at Madeleine Road for up to 2 days in early July
  • Intermittent lane and footpath closures until late July
  • Pedestrian detours in place
  • Increased truck movements
  • Service relocation
Madeleine Road, Clayton Day/night works: Ongoing until late July
  • Site establishment
  • Intermittent lane and footpath closures
  • Pedestrian detours in place

Oversized deliveries

There will continue to be large equipment and machinery delivered to the Clayton worksite. Most deliveries can be moved on a normal truck load during the day, however there will be some oversize loads delivered at night to reduce traffic impacts.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction.

The Project supports businesses and residents to continue to live, work, study and shop in their community. Clayton shopping precinct remains open and accessible throughout these works.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

  • Maintaining access for emergency vehicles and buses at all times
  • Maintaining access to homes and businesses
  • Safely removing hazardous materials in accordance with Environmental Protection Authority regulations
  • Transporting materials from site in covered trucks to minimise dust
  • Using water and dust suppressants
  • Installing road safety and detour signage
  • Pedestrian and cyclist detours in place.