17 June 2026 to 1 October 2026

Works are underway in Clayton to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
24 hour works: 7am Monday to midnight Saturday

The following works will be carried out between July and September 2026.

WhereWhen What we are doing What to expect
SRL worksite, Clayton Road, Clayton

24 hour works: Ongoing

  • Excavating the station site
  • Utilities connections
  • 24 hour works from 7am Monday to midnight Saturdays
  • Increased truck and heavy vehicle movements
  • Moderate levels of noise, light, dust and vibration
  • Intermittent overnight deliveries

Clayton Road, Clayton

Day works: Ongoing 
  • Signal modification works
  • Site maintenance
  • Lane closures between Colonel Street and Dunstan Street
Carinish Road, Clayton Day works: Ongoing
  • Signal modification works
  • Site maintenance
  • Lane closure between Clayton Road and Mary Street for up to 2 days
  • Intermittent lane and footpath closures
Link Road, Clayton Day works: Ongoing
  • Site maintenance
  • Intermittent lane and footpath closures
Madeleine Road, Clayton Day works: Ongoing
  • Site maintenance
  • Utilities connections
  • Intermittent lane and footpath closures

Note: Timing of works may change due to weather or ground conditions.

Additional short term traffic changes will be in place around the Clayton area as we complete site investigation works in the area.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction.

The Project supports businesses and residents to continue to live, work, study and shop in their community. Clayton shopping precinct remains open and accessible throughout these works.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

  • Maintaining access for emergency vehicles and buses at all times
  • Maintaining access to homes and businesses
  • Transporting materials from site in covered trucks to minimise dust
  • Using water and dust suppressants
  • Installing road safety and detour signage
  • Pedestrian and cyclist detours in place.