24 September 2025 to 1 November 2025

Works are underway in Glen Waverley to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Night works 6pm to 7am Monday to Sunday
Extended works 1pm to 5pm Saturday and 7am to 1pm Sunday

The following works will be carried out during October.

WhereWhen What we are doing What to expect
Coleman Parade, Glen Waverley Day/Extended works: Ongoing until late October 2025
  • Commissioning services
  • Reinstatement works
  • Road closure between east of Carramar Avenue and Kingsway
  • Up to 60 commuter car spaces closed
  • Traffic management and pedestrian detours
  • Changes to 737 bus route (visit ptv.vic.gov.au to plan your journey)
  • Medium levels of noise
Myrtle Street, Glen Waverley

Day/Extended works: Ongoing until late 2025

  • Moving underground
  • Road realignment
  • Commissioning services
  • Road closure between Coleman Parade and Bogong Avenue
  • Traffic management and pedestrian detours
  • Medium levels of noise
  • High levels of vibration
Montclair Avenue car park, Glen WaverleyDay/Extended works: Intermittently until October 2025

Night works: From early October 2025 for up to 3 nights
  • Moving underground services
  • Reinstatement works
  • Up to 5 car spaces closed within the Montclair Avenue car park
  • Traffic management and pedestrian detours
  • Medium levels of noise
  • Light spillage
Montclair Avenue, Glen Waverley

Day/Extended works:
Ongoing until late October 2025

Night works: From early October 2025 for up to 3 nights

  • Moving underground services
  • Road realignment
  • Road modifications
  • Road closure between Myrtle Street and west of Kingsway
  • Intermittent lane closures between east of Florence Street and Kingsway
  • Traffic management and pedestrian detours
  • Medium levels of noise
Bogong Avenue, Glen WaverleyDay/Extended works:  Ongoing until late October 2025
  • Closing on street parking spaces to facilitate traffic flow during works
  • Up to 20 on street car spaces will be closed
Florence Street, Glen WaverleyDay/Extended works:  Ongoing until late October 2025
  • Closing on street parking spaces to facilitate traffic flow during works
  • Up to 20 on street car spaces will be closed

Note: Timing of works may change due to weather or ground conditions.

Glen Waverley Traders will be open for business during works.

Glen Waverley day and night works,ongoing until late October 2025

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Maintaining access to the the Waverley RSL, Glendale Street and Montclair Avenue car parks
  • Transporting materials from site in covered trucks to minimise dust
  • Installing road safety and detour signage
  • Maintaining access to homes and businesses
  • Monitoring noise, dust and vibration levels
  • Turning off equipment when not in use
  • Using noise blankets on equipment
  • Using water and dust suppressants
  • Minimising light spill
  • Coordinating disruptions with other construction companies in the area.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Glen Waverley.

Sign up for SMS notifications

Thank you for your patience and cooperation as we progress the delivery of SRL East at Glen Waverley.