24 January 2025 to 28 February 2025

Works are underway in Heatherton and Clarinda to deliver Suburban Rail Loop (SRL) East  for Melbourne and Victoria.

We are building a Stabling Facility in Heatherton and preparing to launch Tunnel Boring Machines (TBMs) from Clarinda.

Upcoming works at these sites are summarised below:

Stabling Facility in Heatherton

  • Building the Eastern Tunnel Entrance (ETE) and Western Tunnel Entrance (WTE)
  • Building a permanent Network Support Facility (NSF) for construction and operational power
  • Moving underground and above ground services

Clarinda

  • Site investigations, site establishment and building a temporary power supply facility to power the TBMs
  • Building the Clarinda Tunnel Access Structures (TAS)

What we are doing

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Night works: 6pm to 7am Monday to Friday
Extended works: 6pm to 10pm Monday to Friday, 1pm to 5pm Saturday and Sunday.
24-hour works at times.

WhereWhen What we are doing What to expect
Stabling Facility 

Day/night and extended works: Ongoing

  • Building the ETE, WTE and NSF
  • Site investigations
  • Safety removing hazardous materials
  • Establishing a worksite, including excavation, tree removal and drainage works
  • Installation of permanent fencing
  • Moving underground services
  • Lane and road closures on Elder Street South and Henry Street until early February
  • From mid February to late 2025 there will be 24-hour works, 7am Monday to 7am Sunday to prepare and excavate the ETE
  • You may see workers in specialised protective clothing as we continue safe removal of hazardous materials
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements
Clarinda Day/night and extended works: Ongoing 
  • Building the TAS and temporary power supply facility
  • Safely removing hazardous material
  • Establishing a worksite, including traffic barrier installation, earthworks and tree removal
  • Installation of permanent fencing
  • Construction activities and piling
  • Road lighting installation
  • Road modifications and asphalting
  • You may see workers in specialised protective clothing as we continue safe removal of hazardous materials
  • Increased levels of noise, vibration, light and dust
Kingston RoadDay/night/extended works: Ongoing 
  • Moving underground services
  • Establishing a worksite, including permanent fencing installation, and tree and vegetation removal
  • Traffic barrier installation
  • Road modifications and asphalting
  • Westbound lanes closed between Old Dandenong Road and Dingley Bypass until late March with crews working 24-hours
  • No right turn from Kingston Road onto Old Dandenong Road from early February until mid March 2025
  • Overnight road closure for up to 2 nights between Pine Lane and Dingley Bypass from early February
  • Westbound lanes closed for up to 2 nights between Pietro Road and Dingley Bypass from early February
  • Overnight road closure for up to 3 nights between Nicholas Grove and Pietro Road from mid February
  • Changed traffic conditions day and night between Nicholas Grove and Clayton Road, with traffic management and detours in place
  • Access to homes and businesses will be maintained
  • Moderate levels of noise, vibration, light and dust
  • Changes to 631 bus route
  • Closure of some bus stops between Pine Lane and Clayton Road

Visit ptv.vic.gov.au to plan your journey

Old Dandenong RoadDay/night/extended works: From early February until mid March 2025
  • Moving underground services
  • Road modifications and asphalting
  • Southbound lanes closed between Kingston Road and Madden Road with crews working 24-hours
  • Changed traffic conditions, with traffic management and detours in place
  • Access to homes and businesses will be maintained
  • Moderate levels of noise, vibration, light and dust

Note: Timing of works may change due to weather or ground conditions.

Grow Master, Diaco's and Kingston Heath Golf Club will be open for business during works.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Transporting materials from site in covered trucks to minimise dust
  • Safely removing hazardous materials in accordance with EPA regulations
  • Scheduling works to reduce impacts
  • Maintaining access to homes and businesses
  • Monitoring noise, dust and vibration levels
  • Minimising light spill
  • Turning off equipment when not in use
  • Using noise blankets on equipment
  • Using water and dust suppressants.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton and Clarinda.