25 June 2025 to 1 August 2025

Works are underway in Heatherton and Clarinda to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Stabling Facility in Heatherton

  • Building the Eastern Tunnel Entrance (ETE) and Western Tunnel Entrance (WTE)
  • Building a permanent Network Support Facility (NSF)
  • Moving underground and above ground services.

Tunnel Boring Machine (TBM) launch site, Clarinda

  • Building the Clarinda Tunnel Access Structure (TAS)
  • Connecting underground services.

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday

Extended works: 6pm to 10pm Monday to Saturday
Night works: 6pm to 7am Monday to Saturday
24 hour works: 7am to 7am Monday to Sunday

WhereWhen What we are doing What to expect

Stabling Facility West, Heatherton

Day works: Ongoing to late 2025
Extended works: Early July to late 2025
  • Building the WTE including office mobilisation, earthworks, concreting, commence guide wall construction, compacting, drainage works, machinery assembly, piling and hoarding installation
  • Site investigations
  • Safe removal of hazardous material

To safely deliver works, some construction activities including concrete pouring will need to be undertaken until 10pm

  • Workers in specialised protective clothing as we continue safe removal of hazardous materials
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements and delivery of large machinery for up to 3 nights
Stabling Facility East, Heatherton 24 hour: Ongoing to late 2025
  • Building the ETE, with 24 hour excavation and related works
  • Building the NSF
  • Site investigations
  • Changed traffic conditions on Henry Street until mid-July
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements
Kingston Road, Heatherton

Day/night works: Ongoing to late 2025

  • Moving and connecting underground and above ground services
  • Traffic barrier movements
  • Site deliveries via Kingston Road
  • Westbound lanes closed between Old Dandenong Road and Dingley Bypass ongoing to early July
  • No right turn onto Old Dandenong Road ongoing to early July
  • Overnight road closures between Nicholas Grove and Dingley Bypass for traffic barrier movements at times from early July to late July
  • Changed traffic conditions day and night between Golf View Road and Clayton Road with traffic management and detours in place
  • Moderate levels of noise, vibration, light and dust
  • Changes to 631 bus route including closure of some bus stops between Nicholas Grove and Clayton Road
  • Visit ptv.vic.gov.au to plan your journey
Old Dandenong Road, Heatherton Day/night works: Ongoing to late 2025
  • Moving and connecting underground services
  • Road reinstatement
  • Traffic barrier movements
  • Southbound closure and northbound lane closure between Kingston Road and Madden Road ongoing to early July. Northbound traffic maintained
  • Overnight road closure between Kingston Road and Madden Road for up to 4 nights from mid July to late July
  • Overnight road closure between Kingston Road and Madden Road for up to 2 nights for traffic barrier movements in early July.
  • Changed traffic conditions, with traffic management and detours in place
  • Moderate levels of noise, vibration, light and dust
TBM launch site, Clarinda 24 hour: Ongoing to late 2025
  • Building the Clarinda TBM launch site, including civil works, backfilling of ponds, d-walling and ground improvement
  • Changed traffic conditions on Peace Road and Victory Road
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements day and night

Note: Timing of works may change due to weather or ground conditions.

Local traders remain open for business during works.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Covering trucks to minimise dust
  • Monitoring noise, dust and vibration levels
  • Using noise blankets and hoarding to minimise noise, dust and light spill
  • Safely removing hazardous materials in accordance with regulations
  • Using water and dust suppressants
  • Maintaining access to homes and businesses.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton and Clarinda.