27 October 2025 to 1 December 2025

Works are underway in Heatherton and Clarinda to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Train stabling facility, Heatherton

  • Building the eastern tunnel entrance (ETE) and western tunnel entrance (WTE)
  • Building a permanent network support facility (NSF)
  • Moving underground and above ground services.

Tunnel Boring Machine (TBM) launch site, Clarinda

  • Building the Clarinda tunnel access structures (TAS)
  • Connecting underground services.

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Extended works: 6pm to 10pm Monday to Friday and 1pm to 10pm Saturday
Night works: 6pm to 7am Monday to Sunday
24 hour works: 7am to 7am Monday to Sunday

WhereWhen What we are doing What to expect

Train stabling facility west, Heatherton

Day works: Ongoing to late 2025
Extended works: Ongoing to late 2025
  • Building the WTE including earthworks, concreting and diaphragm wall construction
  • Site investigations
  • Safe removal of hazardous material
  • Extending hoarding
  • Tree removal
  • To safely deliver works, some construction works including concrete pouring will need to be undertaken until 10pm
  • Workers in specialised protective clothing as we continue safe removal of hazardous materials
  • Workers in Kingston Walk Linear Reserve and Henry Street Linear Reserve at times for site investigations
  • Moderate levels of noise, vibration, light and dust
  • Truck movements
Train stabling facility east, Heatherton 24 hour: Ongoing to late 2025
  • Building the ETE, with 24-hour excavation and related works
  • Building the NSF
  • Site investigations
  • Safe removal of hazardous materials
  • Tree removal
  • Workers in specialised protective clothing as we continue safe removal of hazardous materials
  • Moderate levels of noise, vibration, light and dust
  • Truck movements
Dingley Bypass, Heatherton

Night works: Late November 2025 for up to 5 nights

  • Moving and connecting underground services
  • Intermittent northbound overnight road closures between Clarinda Road and Kingston Road for up to 5 nights
  • Intermittent southbound overnight lane closures between Clarinda Road and Kingston Road for up to 5 nights
Kingston Road, Heatherton

Day/night works: Ongoing to late 2025

  • Road reinstatement
  • Lighting installation
  • Moving and connecting underground and above ground services
  • Traffic barrier movements
  • Hoarding construction
  • Intermittent overnight road closures from Nicholas Grove to Clayton Road from late October to late November for up to 7 nights
  • Eastbound lane closure between Dingley Bypass and Clayton Road from early November for up to 6 weeks
  • Changed traffic conditions between Nicholas Grove and Clayton Road with traffic management in place until early 2026
  • Changes to 631 bus route including closure of some bus stops between Nicholas Grove and Clayton Road
  • Access to homes and businesses will be maintained
  • Moderate levels of noise, vibration, light and dust
  • Visit ptv.vic.gov.au and bigbuild.vic.gov.au/disruptions to plan your journey
TBM launch site, Clarinda 24 hour: Ongoing to late 2025
  • Building the Clarinda TBM launch site, including civil works, concrete slab construction, diaphragm wall construction, piling and ground improvement
  • Moving and connecting underground services
  • Changed traffic conditions on Victory Road
  • Peace Road entry at Kingston Road closed from late October for up to 6 weeks. Entry to Peace Road via Victory Road
  • Moderate levels of noise, vibration, light and dust
  • Truck movements day and night

Note: Timing of works may change due to weather or ground conditions.

Local traders remain open for business during works.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

  • Covering trucks to minimise dust
  • Monitoring noise, dust and vibration levels
  • Using noise blankets and hoarding to minimise noise, dust and light spill
  • Safely removing hazardous materials in accordance with regulations
  • Using water and dust suppressants
  • Maintaining access to homes and businesses.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton and Clarinda.