25 June 2025 to 1 August 2025

Works are underway in Monash to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Night works 6pm to 7am Monday to Saturday
Day works 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Extended works 6pm Friday to 7am Monday

WhereWhen What we are doing What to expect

SRL worksite on Normanby Road, Notting Hill

Day works: Ongoing until early 2026

  • Site establishment
  • Demolishment of existing buildings
  • Site investigations
  • Tree removal
  • Building a network support facility
  • Moderate levels of noise, vibration and dust

Ferntree Gully Road, Notting Hill

Night and extended works: Ongoing until early July

  • Moving services
  • Road modifications
  • Changed traffic conditions, including lane closures and overnight road closures

Howleys Road, Notting Hill

Day works: Ongoing until December

Night/Extended works: Ongoing until late July

  • Site investigations
  • Hoarding installation
  • Tree removal
  • Moving services
  • Cable installation
  • Road modifications
  • Moderate levels of noise and vibration
  • Changed traffic conditions including intermittent lane closures and overnight road closures
  • Pedestrian detours
  • Increase truck movements
  • On street parking space closures
  • 24/7 intersection closure at Ferntree Gully Road until early July

Normanby Road, Notting Hill

Day and night works: Ongoing until mid 2025

  • Moving services
  • Cable installation
  • Site establishment
  • Intermittent daytime lane closures

Additional traffic changes will be in place around the Notting Hill area throughout mid-2025 as we complete utility relocation works in the area. If there are disruptions to your utility services, you will be notified by your provider directly.

Day works

Night works

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Maintaining access to businesses during businesses hours, with help from traffic controllers where required
  • Staging works along Howleys Road and Normanby Road to minimise traffic disruption
  • Installing road safety and detour signage
  • Notifying bus stop disruptions at the impacted stops ahead of time
  • Transporting materials from site in covered trucks to minimise dust
  • Positioning equipment as far as possible from businesses and residents and turning it off when not in use
  • Safely removing hazardous materials in accordance with EPA regulations
  • Monitoring noise, dust and vibration levels.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Monash.