25 March 2026 to 16 June 2026

Mount Waverley施工最新消息

Works are underway in Mount Waverley to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works 7am to 6pm, Monday to Friday and 7am to 1pm, Saturday

The following works will be carried out during April 2026.

WhereWhen What we are doing What to expect
Emergency support facility site, Mount Waverley Day works: Ongoing until mid June 2026
  • Installing the acoustic shed
  • Traffic management in place
  • Medium to high levels of noise, dust and vibration

Note: Timing of the works may change due to weather or ground conditions.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Accessing site via the gate at High Street Road only
  • Installing road safety and detour signage
  • Transporting materials from site in covered trucks to minimise dust
  • Maintaining access to homes and businesses
  • Installing fencing and hoarding to reduce construction noise and dust
  • Using street sweepers to keep roads clean
  • Using water and dust suppressants
  • Monitoring noise, dust and vibration levels
  • Selecting construction equipment and methodology to reduce noise, dust and vibration impacts to the community
  • Positioning equipment as far as possible from residential properties and turning it off when not in use
  • Scheduling works to minimise impacts

Sign up for SMS notifications

Thank you for your patience and cooperation as we progress the delivery of SRL East at Mount Waverley.