29 May 2025 to 1 July 2025

We’re preparing for works in Mount Waverley to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works 7am to 6pm Monday to Friday and 7am to 1pm Saturday

WhereWhen What we are doing What to expect
Emergency Support facility site, Mount Waverley Day works: Ongoing to September 2025
  • Site investigations including:
    • Non destructive digging (NDD) to excavate into the ground to confirm location of underground services
    • Saw cutting and removing sections of concrete
    • Using small drill rigs to drill boreholes to investigate ground conditions and take ground samples
    • Using equipment to undertake environment, land and other visual surveys and inspections on and around the site.
  • All access to site will be via the existing gate at High Street Road
  • No traffic changes are anticipated as part of these works
  • Medium to high levels of noise associated with NDD, concrete cutting and drilling works
  • Low levels of dust and vibration
  • Workers, machinery and vehicles at the site.
Kiers Avenue,
Mount Waverley
Day works: Late June to early July 2025
  • Site investigations including:
    • NDD to excavate into the ground to confirm location of underground services
    • Saw-cutting and removing sections of concrete
    • Using small drill rigs to drill boreholes to investigate ground conditions and take ground samples.
  • Traffic management in place
  • 4 on-street car spaces closed
  • Medium to high levels of noise associated with NDD, concrete cutting and drilling works
  • Workers, machinery and vehicles at the site.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Installing road safety and detour signage
  • Maintaining access to homes and businesses
  • Monitoring noise, dust and vibration levels
  • Turning off equipment when not in use
  • Using water and dust suppressants.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Mount Waverley.

What's next at the emergency support facility site?

Site establishment, including demolishing existing buildings, removing vegetation, installing fencing and hoarding and building temporary site offices, worker facilities and car parks, will commence from mid 2025. This will be followed by major construction, including piling works and the excavation of the intervention and ventilation shaft.

Before these works start, we will notify and engage directly with residents and businesses to provide further information about upcoming works, what to expect and how disruptions will be managed