25 September 2025 to 1 November 2025

Works are underway in Mount Waverley to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Day works 7am to 6pm Monday to Friday and 7am to 1pm Saturday

The following works will be carried out during October.

WhereWhen What we are doing What to expect
Emergency Support facility site, Mount Waverley Day works: Ongoing until mid October 2025

Site establishment including:

  • Removing trees and vegetation
  • Setting up site offices
  • installing fencing and hoarding
  • Safely removing hazardous materials, if found

Preparing for piling work:

  • Earthworks
  • Traffic management in place
  • Medium to high levels of noise, dust and vibration
  • Workers, machinery and vehicles at the site
  • Transporting construction machinery to site
High Street Road, Mount Waverley Day works: Ongoing until late December 2025
  • Installing temporary traffic signage
  • Intermittent lane closures between Kiers Avenue and Elm Grove between 9.30am and 3pm weekdays
Emergency Support facility site, Mount WaverleyDay works: From mid October to early 2026
  • Piling to construct the intervention and ventilation shaft walls including
    • Drilling 25 metre deep holes
    • Filling the holes with concrete
    • Safely removing hazardous materials, if found
  • Traffic management in place
  • Medium to high levels of noise, dust and vibration
  • Workers, machinery and vehicles at the site

Note: Timing of the works may change due to weather or ground conditions.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Accessing site via the existing gate at High Street Road only
  • Installing road safety and detour signage
  • Transporting materials from site in covered trucks to minimise dust
  • Maintaining access to homes and businesses
  • Installing fencing and hoarding to reduce construction noise
  • Using street sweepers to keep roads clean
  • Using water and dust suppressants
  • Scheduling works to minimise impacts.

Sign up for SMS notifications

Thank you for your patience and cooperation as we progress the delivery of SRL East at Mount Waverley.