6 May 2022 to 30 August 2022
Between now and the end of August, the West Gate Tunnel Project (WGTP) will be continuing works at the Northern Portal on Whitehall Street and throughout Yarraville.
If any of these works are expected to be disruptive, we will be in touch before they begin.
We’re continuing construction work at our Northern Portal site along Whitehall Street between Youell Street and Somerville Road. The Portal is an integral part of the Project’s tunnelling hub with activities being carried out 24/7 to support tunnelling activities. You may notice minor construction noise from within the construction site as well as truck movements to and from the site.
We are also continuing to build sections of the road deck and ventilation ducts. Other construction works include concrete pours, installing precast concrete units and building walls.
| Impact | Date |
|---|---|
| Occasional nightworks (9pm to 5am) | Ongoing |
| Truck movements in the area | Ongoing |
| Minor noise and vibration | Ongoing |
| Occasional lane closures on local Yarraville roads | May – August 2022 |
| Ongoing traffic management on Harris Street between Cowper and Whitehall Street | Ongoing until the end of May 2022 |
| Occasional night-time lighting | May to August 2022 |
More information on what you can expect during these works
Works will be completed primarily during the day with occasional nightworks.
Construction vehicles will be moving in and out of the area including excavators, concrete trucks, cranes and rollers.
Minor vibration and noise may be experienced during these works.
Water-spray trucks and road sweepers will be used in local streets around our worksites, keeping local roads clean during construction.
Changes in traffic conditions may be experienced during these activities.Lighting will be angled away from homes wherever possible whilst we are working at night.
Thank you
We appreciate our work can be disruptive and thank you for your understanding. Works may be rescheduled in the event of unexpected impacts.
For updates or questions, please visit the West Gate Tunnel Project website , call 1800 105 105 or email info@wgta.vic.gov.au