6 July 2020 to 31 December 2022

Reminder notification: Fogarty Avenue shared use path

In April this year we updated you on work we were planning to start in May to build the new shared use path (SUP) which runs from Fogarty Avenue near the reserve.

The SUP will go up and over the Williamstown Road inbound exit ramp via a new bridge which will extend the Federation Trail and connect with the new SUP alongside the Hyde Street inbound ramp.

Construction activity

July 2020 - ongoing

The later than anticipated completion of drainage works at our existing construction site near the reserve at the eastern end of Fogarty Avenue means we can now start construction of the new SUP bridge.

With a project of the scale of the West Gate Tunnel, starting a new set of works often depends on the completion of preceding works in or around the same area, and that has been the case here.

While this work will take place within our existing construction site, the space required for the works will mean the ongoing closure of the SUP that runs over Stony Creek and through the reserve at the eastern end of Fogarty Avenue.

Works to be done from July onwards will include:

  • piling to support the new SUP bridge
  • constructing piers to support the new SUP bridge
  • formwork and concrete pours to create the SUP bridge deck.

This work is part of the West Gate Tunnel Project delivering more than 14km of new and upgraded paths, making it safer and easier for more people to walk or cycle.

Hours of work

Our usual hours of work are Monday to Friday between 7am-6pm, and Saturdays between 7am-1pm. However, night works are sometimes required. When works are scheduled out of hours, or if you are located close to the works, we will provide you with further information before the works start.

What to expect during these works

  • Work will be completed behind safety barriers.
  • Ongoing closure of the SUP over Stony Creek. A signed detour is in place. This SUP will be reopened once we have completed works in the area
  • Construction vehicles including excavators, piling rigs, water trucks and concrete trucks will be moving in and out of the work areas via our access routes
  • Trucks and vehicles continuing to enter and exit our construction sites via local roads
  • Water spray trucks and road sweepers will be used to manage dust and dirt during works. Trucks removing dirt and rock from the site will be covered.
  • Traffic changes including lane and road closures will be required. Signed detours will be in place.

For latest updates, dates of closures and detour route information please visit the Victoria's Big Build Disruptions webpage.

Please note that works are subject to change and may be rescheduled in the event of unexpected impacts to the construction program. Thank you for your patience during these works.