Level Crossing Removal Project business case released

Back to Newsfeed

The Business Case for the Level Crossing Removal Project has been published today, showing the wide-ranging benefits of removing 50 level crossings across Melbourne.

The Level Crossing Removal Project is tasked with removing 50 dangerous and congested level crossings by 2022.

Until now, level crossings have been removed one at a time or in pairs, and over a number of years. While this approach goes some way toward addressing localised issues, the scale of the problem is so big that it calls for a strategic approach and corresponding scale of investment.

The program of crossing removals will have benefits for safety, congestion, and creating better connected, liveable and thriving communities.

The level crossing removal program is a critical enabler of other major rail projects, including the Cranbourne-Pakenham Line upgrade and the Metro Tunnel.

As a standalone program, the Level Crossing Removal Program is expected to deliver a Benefit Cost Ratio (BCR) of 0.78. The combination of the Level Crossing Removal Program, with interdependent projects including the Cranbourne-Pakenham Line upgrade and the Metro Tunnel, is expected to deliver a net benefit of $5.1 billion and a BCR of 1.2.

But removing level crossings is about more than economics, it is also about saving lives. 20 people died after being hit by a train between 2005 and 2014 at one of the 50 crossings slated for removal, with more than 60 collisions and nearly 680 near misses also occurring at those 50 sites.

Together, this pipeline of projects will transform Melbourne's transport network and the future shape of Melbourne.

10 level crossings have already been removed, a further 13 are underway and all 50 will be removed by the end of 2022.

Read the Program Business Case.