Between early 2020 and mid 2022, specialist crews moved almost 100 above and underground services to make way for North East Link.
The Early Works program involved relocating power, water, gas, sewer and telecommunication services, as well as preparing future work sites and building new infrastructure to support the next stage of construction.
To date, crews have relocated:
Here are some of the highlights from our Early Works program:
3 mini tunnel boring machines (TBMs) moved 1.8km of the Yarra East Main Sewer to the east of Bulleen Road, beneath homes, schools and sports clubs in Bulleen.
We relocated utilities along the Eastern Freeway in Kew East, Balwyn North, Bulleen and Doncaster.
We relocated utilities including important water supply infrastructure around Borlase Reserve in Yallambie.
We laid gas pipes and power lines on Greensborough Road at night and restored the road for traffic each morning in Macleod.
We replaced buildings and services, including transplanting 2 Lone Pines to a new ANZAC Day Service Area, on land provided by the Australian Government in Yallambie.
We moved a mobile phone tower and 2 high-voltage towers, by carefully stringing live power lines over Greensborough Highway in Watsonia.