1 June 2025

With both Tunnel Boring Machines relaunched towards Bulleen, we're continuing works on Lower Plenty Road upgrading the Silk Street pedestrian bridge.

What we'll be doing

As the Tunnel Boring Machines (TBMs) progress, we’ll construct cross passages between the 2 tunnels.

We’ll perform excavation and break through existing concrete walls underground to build multiple cross passages along the tunnel route. These passages will provide access between tunnel in the unlikely event of an emergency.

Activities to support tunnelling works will take place 24 hours a day, 7 days a week. You may notice some noise and vibration at times during the day or night while works are completed near you.

We’ll aim to minimise noise and light impacts away from your property as much as possible

Managing construction impacts

Throughout our works, you may experience noise, light, dust, and vibration. We manage these impacts through real time monitoring, water carts and street sweepers, targeted lighting, and reducing noise and vibration within the construction zone. You may also see workers and machinery, in and around construction areas, and an increase of trucks removing dirt from our worksites.

To stay safe, please follow all instructions from signage and traffic controllers. We appreciate your patience and understanding throughout these works.

Track our TBMs

Our TBMs are powering ahead, excavating the North East Link Tunnels from Watsonia to Bulleen. Both TBMs will take planned breaks throughout their journey from Watsonia to Bulleen to undertake regular maintenance. You can track their progress at Tunnel boring machines tracker.

M80 Ring Road Completion upcoming disruptions

There'll be intermittent lane closures and speed reductions in place along Greensborough Highway, Greensborough Bypass, M80 Ring Road, Grimshaw Street and Plenty Road until late 2025.

At Grimshaw Street, crews will work at times during the day and night, with road closures and detours in place in July and August while we relocate underground utility services.

On Watsonia Road, intermittent lane and road closures will be required at times and on local roads, such as Service Road and Dennett Street in Watsonia. Sections of the M80 Ring Road Trail and Greensborough Bypass Path are closed with temporary long term detours in place.

Please plan your trip and allow additional travel time. Search the Disruptions map for the latest information on traffic disruptions.

Sign up for SMS updates

We'll keep using works notices to keep you up to date. You can now also sign up to SMS updates to hear about any unexpected changes and traffic near you. To register, text 'Watsonia' or 'Yallambie' to 0447 251 237.

Alternatively, visit our subscribe page.

Keeping in touch

We’ll be out talking to nearby residents and businesses about these works in more detail, including how we’ll be managing any local impacts. If you have any questions now, please contact the NELP 24/7 Contact Centre on 1800 105 105.

Stay informed of upcoming disruptions in your area by visiting the disruptions page.


Map of works area


Schedule is subject to change. Visit our work notices page for schedule changes. For more information call 1800 105 105 or visit the Hub at 17 Watsonia Road, Watsonia.