25 July 2025 to 1 September 2025

Works are underway in Heatherton and Clarinda to deliver Suburban Rail Loop (SRL) East for Melbourne and Victoria.

What we are doing

Stabling Facility in Heatherton

  • Building the Eastern Tunnel Entrance (ETE) and Western Tunnel Entrance (WTE)
  • Building a permanent Network Support Facility (NSF)
  • Moving underground and above ground services.

Tunnel Boring Machine (TBM) launch site, Clarinda

  • Building the Clarinda Tunnel Access Structure (TAS)
  • Connecting underground services.

Day works: 7am to 6pm Monday to Friday and 7am to 1pm Saturday
Extended works: 6pm to 10pm Monday to Saturday
Night works: 6pm to 7am Monday to Sunday
24 hour works: 7am to 7am Monday to Sunday

WhereWhen What we are doing What to expect

Stabling Facility West, Heatherton

Day works: Ongoing to late 2025
Extended works: Early to late 2025
  • Building the WTE including earthworks, concreting, guide wall construction, compacting and piling
  • Site investigations
  • Safe removal of hazardous material

To safely deliver works, some construction works including concrete pouring will need to be undertaken until 10pm

  • Workers in specialised protective clothing as we continue safe removal of hazardous materials
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements and delivery of large machinery
Stabling Facility East, Heatherton 24 hour: Ongoing to late 2025
  • Building the ETE, with 24-hour excavation and related works
  • Building the NSF
  • Site investigations
  • Road reinstatement
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements
  • Changed traffic conditions on Henry Street with traffic management in place until mid August
Kingston Road, Heatherton

Day/night works: Ongoing to late August 2025

  • Road reinstatement
  • Site deliveries
  • Service connections
  • Moving and connecting underground and above ground services
  • Traffic barrier movements
  • Intermittent overnight road closures between Nicholas Grove and Clayton Road from late-July to late-August
  • Changed traffic conditions between Golf View Road and Clayton Road with traffic management in place
  • Moderate levels of noise, vibration, light and dust
Old Dandenong Road, Heatherton Day/night works: Early August to mid August
  • Moving and connecting underground and above ground service
  • Lane closures for up to one week between Kingston Road and Madden Road from early- August to mid-August. Traffic maintained in both directions
TBM launch site, Clarinda 24 hour: Ongoing to late 2025
  • Building the Clarinda TBM launch site, including backfilling of ponds, piling, ground improvement and diaphragm wall construction
  • Changed traffic conditions on Peace Road and Victory Road
  • Moderate levels of noise, vibration, light and dust
  • Increased truck movements day and night

Note: Timing of works may change due to weather or ground conditions.

Local traders remain open for business during works.

Impacts

As with all major infrastructure projects, surrounding communities may experience some impacts during construction. The Project supports businesses and residents to continue to live, work, study and shop in their community.

Please contact us on 1800 105 105 to discuss support available if you are impacted by our works.

How we will manage our works

We will minimise impacts to the community by:

  • Covering trucks to minimise dust
  • Monitoring noise, dust and vibration levels
  • Using noise blankets and hoarding to minimise noise, dust and light spill
  • Safely removing hazardous materials in accordance with regulations
  • Using water and dust suppressants
  • Maintaining access to homes and businesses.

Thank you for your patience and cooperation as we progress the delivery of SRL East at Heatherton and Clarinda.

Help us improve the website by completing a short survey

Close