A massive construction blitz will see trains travelling at higher speeds on the Echuca Line before the year’s end.
Coaches will replace Echuca Line trains between Bendigo and Echuca from Wednesday 1 September to Sunday 31 October to enable major works to take place on the Bendigo and Echuca Line Upgrade.
The track upgrades will allow trains to travel at up to 130km/h between Epsom and the new Goornong Station, up from the 80km/h they travel currently, enabling people to get where they need to go sooner.
John Holland has been appointed to deliver the track upgrades, which include replacement of more than 20,000 sleepers, new ballast, drainage improvements, rail bridge upgrades, mud-hole removal and level crossing modifications to boost safety.
Trains will still run between Bendigo and Epsom for local passengers.
Deliveries of new ballast and concrete sleepers have commenced along the line ahead of track works starting on 1 September.
Construction of the new Victorian Government-funded stations at Goornong and Huntly will also commence while trains aren’t running.
Critical works including track alignment and platform construction will take place at the new stations.
The new station at Goornong is targeted for completion by the end of the year, with Huntly to follow in mid-2022 and Raywood Station on the Swan Hill Line at the end of 2022.
Development of the new electronic train order (ETO) system being delivered by V/Line as part of the Bendigo and Echuca Line Upgrade is also progressing, which will allow additional weekday return services to both Eaglehawk and Epsom, and triple the number of weekday services to and from Echuca after completion in late 2022.
The Bendigo and Echuca Line Upgrade is part of the $4 billion Regional Rail Revival program, which is upgrading every regional passenger rail line in Victoria and creating 3,000 jobs and local supplier opportunities.