UNDER CONSTRUCTION

Site establishment on Greens Road service road and utility relocations

Upgrading the intersection of Ballan, McGrath and Greens roads in Wyndham Vale.

To prepare for the upgrade, we’ll build a project site office and compound in the grassy reserve area off Greens Road service road between McGrath Road south and Wembley Street. We’ll also undertake other works around the roundabout to prepare for major construction in early 2026.

What we’ll be doing and when

From Thursday 6 November to early December, we’ll work mostly during the day, from 7am to 6pm, to build our site compound, which will be used by our workers throughout the project.

Throughout November and December, we’ll also start to relocate underground services. To safely do this work, we’ll close lanes at times.

What you can expect

During these works, you may notice:

  • construction noise
  • more workers, vehicles and equipment moving in and out of the area.

Change to parking on service road

To allow vehicles to safely enter and exit our site compound, and to prevent any risk of damage to parked cars, on-street parking on Greens Road service road will be removed for the duration of the project. We understand this may be inconvenient for some residents, but this restriction is necessary for everyone’s safety. Thank you for your understanding and cooperation.

Changes to pedestrian crossing

The existing pedestrian crossing on Ballan Road that leads to the Greens Road service road will be closed for the duration of the project. This path will be used by construction workers to access the site compound. Closing the crossing to the public protects both the community and workers while still providing alternative routes. Pedestrians can continue to use footpaths and crossings on the other legs of the roundabout.

Site preparation works

We’ll remove some vegetation as part of preparing the area for major construction in 2026 and to install our site compound. We’ll replant vegetation once major works are complete.

Some of these works are weather-dependent and can only be completed in dry weather conditions or may be impacted by unexpected ground conditions. If we need to reschedule, we’ll let you know of any changes via email, SMS and on-road signage.