Murray Basin Rail Project

Current works

When
What

March 17 - 21 17 03 2025

Ouyen Rail Yard Works March 2025 (PDF, 240.4 KB)

– safely disconnecting and removing a pipe from the water mains
– completing the excavation of a cess drain
– pouring concrete to create a surface finish that allows water runoff

From September 2024 18 03 2025

Tourello Loop signalling works 2025 (PDF, 276.6 KB)

– Trenching and boring to enable installation of new power and data cables
– Installing new equipment, including signals and axle counters to detect trains
– Construction of access tracks to enable maintenance activities
– Delivery of quarry products and other materials to support these activities

January to June 2025 18 03 2025

Maryborough signalling upgrade June 2025 (PDF, 308.3 KB)

– Installing new signalling equipment, including signals, underground signal cables, and
vegetation removal to allow for these works
– Removing redundant signals and equipment
– Track upgrade works in Maryborough Yard
– Construction of access tracks to enable maintenance activities.