What’s happening
Since our last update, we’ve:
- finished upgrading the intersection at Dellamore Boulevard
- finished building the new eastbound lanes on Somerton Road near Mickleham Road, and shifted traffic onto the new lanes
- finished sections of the new walking and cycling path on Somerton Road near Mickleham Road
- finished relocating gas services between Hillview Road and Dellamore Boulevard
- opened the new connection between Horizon Boulevard and Montenegro Road
- started drainage works at Hillview Road, in preparation for intersection upgrade works
- started building the new westbound lanes on Somerton Road at the intersection of Mickleham Road.
Current and upcoming disruptions
Project timeline
What to expect
Changed traffic conditions
There are changed traffic conditions including reduced speed limits, lane closures and temporary traffic barriers, traffic lights and temporary line marking on Mickleham and Somerton roads while works take place.
Temporary footpath closures and detours are also in place while we relocate services and build new lanes on Mickleham Road.
Construction impacts
Our construction activities may generate low to medium levels of noise, dust, and vibration at times. We’ll be monitoring impacts to ensure they’re kept to a minimum. Most of these works will take place between 7am and 6pm, Monday to Friday and 7am to 1pm, Saturdays. At times we’ll need to work outside of these hours to minimise impacts on traffic during the day. The progress of these works will depend on weather and ground conditions.