UNDER CONSTRUCTION

Project update

Watson Street Interchange Upgrade

For information relating to works along Epping-Kilmore Road please refer to Inland Rail or the Department of Transport and Planning.

From October until late December, we’ll continue to:

  • install new drainage
  • build new kerbs, channels and road pavement
  • install new traffic signals and street lighting
  • install new overhead sign structures and directional signs on the Hume Freeway
  • build the new south-facing freeway ramps.

From 5am Wednesday 11 November, both north-facing ramps will reopen during the day and will close when required during overnight works.

Current and upcoming works

We’ll work during the day and at night to complete these activities safely while reducing impacts on traffic.

Works may change due to weather. We’ll provide updates about significant traffic changes through SMS, email and on-road electronic signs.

Nearby residents and businesses may notice periods of noise, dust and vibration. We’ll monitor our work and take practical steps to reduce disruption where possible.

We’ll maintain access to homes and businesses and continue to coordinate closely with emergency services throughout the works. We’ll also maintain access for people walking and cycling, with signed detours in place when needed.

Please allow extra travel time and follow reduced speed limits, traffic signs and directions from traffic controllers.