Current and upcoming disruptions
Works notices
November 2024 20 11 2024
Marshall Bus Loop November 2024 (PDF, 281.5 KB)
Further asphalt works will be occurring on the bus loop at Marshall Station, which will be closed to buses from Thursday, 28 November to Thursday, 12 December.
Marshall Station
October 2024 18 09 2024
Marshall Station October works (PDF, 229.4 KB)
— finishing works in the forecourt area including fencing
— completion and commissioning of the lifts
— landscaping, including hydroseeding and tree planting at the station and along Station Road
— ongoing construction of the walking and cycling path, including installation of street lighting
— footpath and car park works at the Drews Road entrance
— pavement and civil works at the bus loop intersection with Marshalltown Road.
Marshall Station
October 2024 18 09 2024
Surf Coast Highway October works (PDF, 223.8 KB)
— installation of fencing and gates
— landscaping, including hydroseeding, and tree planting
— construction of two rain gardens
— continued construction of new walking and cycling path
— installation of street lighting
— ongoing basin works at Surf Coast Highway west.
Surf Coast Highway level crossing
October 2024 18 09 2024
Fyans Street October works (PDF, 220.4 KB)
— walking and cycling path finishing works
— landscaping, including hydroseeding, and tree planting
— permanent streetlight commissioning
— line-marking
— fencing and access gate installation
— minor drainage and swale finishing works.
Fyans Street level crossing
October 2024 18 09 2024
South Geelong Station October works (PDF, 292.2 KB)
— station finishing works
— commissioning of the lifts
— landscaping and tree planting
— permanent lighting, communications, and system network commissioning
— line marking
— finalising car park entry/exit at Yarra and Verner streets.