COMPLETE

Burke Road, Glen Iris

The Burke Road, Glen Iris level crossing was removed by lowering the rail line below Burke Road.

A new Gardiner Station, with lowered station platforms accessible by lifts and stairs, was also built.

The project included the consolidation of tram stops near the station on Burke Road and the addition of new walking and cycling paths nearby.

Timeline

The level crossing was removed and station opened in January 2016. All work at the crossing and station sites was finished by August 2016.