To take full advantage of the extra capacity on the rail network created by the Metro Tunnel and its new High Capacity Metro Trains, a range of upgrades are proposed on the Sandringham, Cranbourne and Pakenham lines.

Sign up to our enews and select 'south eastern rail lines' to receive work notifications by email.

Work details

Location and timingDetails

Rail corridor works

Between Caulfield Station and Lightwood Road, Springvale

Thursday 27 January to Monday 21 February 2022

  • 7am to 5pm, Monday to Friday and 7am to 1pm, Saturdays

As part of Metro Tunnel works, we will be undertaking rail asset installation within the rail corridor between Caulfield Station and Lightwood Road, Springvale.

What we are doing

  • Installing rail assets including safety bollards throughout the corridor between Caulfield Station and Lightwood Road
  • Connecting the existing underground cables and conduits to the previously installed relocatable equipment building (REB) between Rayhur Street and Lightwood Road
  • Works will require the use of a non-destructive digging truck, an elevated work platform, a small excavator and crews with hand tools.

What you should be aware of

  • Traffic management will be in place at Westall and Springvale stations, Rayhur Street, Newcomen Road, Queens Avenue and along the Djerring Trail. There are no planned road or shared user path closures while we undertake these works. Any closure will be notified for closer to the date
  • Some parking at Westall and Springvale stations, Rayhur Street, Newcomen Road and Queens Avenue will be temporarily unavailable to support works
  • Works are expected to generate low to medium levels of noise.