Four tunnel boring machines (TBMs), each weighing more than 1100 tonnes and 120m long, were used to dig the twin 9km tunnels.
The TBMs were fitted with drill-like cutterheads measuring 7.3m across, which could tunnel through rock 6 times harder than concrete.
The TBMs dug up to 40m below ground level, with the deepest point under Swanston Street, at the northern edge of the CBD, where the new tunnels pass under the City Loop tunnels.
Find out more about our TBMs.
The designs for the 5 Metro Tunnel stations were an international collaboration between Australian architects Hassell and London-based firms Weston Williamson and Partners and Rogers Stirk Harbour and Partners (RSHP).
Victorians helped name the Metro Tunnel’s 5 new stations: Arden, Parkville, State Library, Town Hall, and Anzac.
An advisory panel made up of a diverse group of Victorians went through over 50,000 suggestions and compiled a shortlist of names for the Victorian Government to consider.
The names chosen were among the most popular suggestions for each station. All names had to meet the naming rules for places in Victoria.
Anzac/ANZAC can be written as either upper or lower case – there is no rule or law around how it is written.
The name Anzac Station is consistent with how the Department of Veterans’ Affairs uses the word.
The Department capitalises “ANZAC” when specifically referring to the Corps. In other circumstances it uses the lower case “Anzac”.
The Metro Tunnel’s new stations are accessible and inclusive. Accessibility features at the stations include:
- escalators and lifts
- customer service counters and Customer Help Points
- Tactile Ground Surface Indicators
- braille and tactile signs
- audible announcements and hearing loops
- improved Passenger Information Displays
- accessible toilets, ambulant cubicles and Changing Places
Find out more about accessibility in the stations.
From 1 February 2026, the Cranbourne, Pakenham and Sunbury Line will run via the Metro Tunnel instead of the City Loop, with dedicated trains.
If you catch trains on other lines, see our interactive map to find out you will be able to change to services running through the Metro Tunnel.
All trains running through the Metro Tunnel will be High Capacity Metro Trains (HCMTs). These trains were specifically designed to align with the platform screen doors at Metro Tunnel stations.
V/Line trains, freight trains and passenger trains that run on other parts of Melbourne’s metropolitan network will not run through the Metro Tunnel.
Having a dedicated line means disruptions on other parts of the network won’t impact Metro Tunnel services (and vice versa).