About the project
The Metro Tunnel means more ways to move around Melbourne, new connections and more choice.
Trains will start running through the Metro Tunnel in early December 2025, stopping at the 5 new underground train stations.
From 1 February 2026, the Cranbourne, Pakenham and Sunbury Line will run through the new tunnels under Melbourne’s CBD.
The project is delivering:
- twin 9km rail tunnels connecting the Sunbury and Cranbourne and Pakenham lines
- 5 new underground stations at Arden, Parkville, State Library, Town Hall and Anzac
- underground pedestrian links to Flinders Street and Melbourne Central stations for easy interchange with the City Loop
- Melbourne’s first tram/train interchange at Anzac Station on St Kilda Road
- High Capacity Signalling allowing for turn-up-and-go services during peak times
- safety features including platform screen doors.
Project milestones
Planning and procurement stage
- April 2015 – Site investigations begin
- February 2016 – Metro Tunnel Business Case released
- June 2016 – Contract awarded for early works
- December 2016 – Environment Effects Statement process finishes
- July 2017 – Contracts awarded for tunnel and stations construction and rail system upgrades
- July 2018 – Contract awarded for rail infrastructure connections and upgrades
Early works stage
- April 2017 – City Square closed as work begins on Town Hall Station
- July 2017 – Toorak Road trams connected to St Kilda Road for construction of Anzac Station
- September 2017 – Demolition and archaeology digs in the CBD begin
- October 2017 – Construction of the first acoustic shed begins (at Franklin Street)
- February 2018 – Grattan Steet closed for construction of Parkville Station
- August 2018 - Piling works at City Square begin
- December 2018 - Federation Square Visitor Centre demolished
Major construction stage
- August 2019 – First tunnel boring machine (TBM) launches at the Arden Station site
- February 2020 – First TBM breakthrough completes a section of tunnel from Arden to Kensington
- July 2020 – New platform at West Footscray Station open
- May 2021 – All TBM tunnelling complete
- February 2022 – Track installation begins
- March 2022 – Sunshine Signal Control Centre completed
- December 2022 – New Anzac Station tram stop open
- March 2023 – Track installation completed with the Metro Tunnel connected to the Cranbourne, Pakenham and Sunbury lines
- January 2024 – Arden Station complete
- May 2024 – Parkville Station complete
- September 2024 – Anzac Station complete
- October 2025 – Town Hall Station and State Library Station complete
Testing stage
- June 2023 – First test trains enter the Metro Tunnel
- October 2023 – High Capacity Signalling introduced on sections of the Cranbourne and Pakenham line
- October 2023– High Capacity Metro Train begin running on the Sunbury Line
- September 2024 - Testing begins with multiple trains in the tunnel
- January 2025 - Trial operations begin including station staff training
- April 2025 - Metro Trains Melbourne staff move into Arden, Anzac and Parkville stations
- October 2025 - Metro Trains Melbourne staff move into State Library Station
Upcoming milestones
- Early December 2025 - Trains will start running through the Metro Tunnel and stopping at all 5 new stations
- 1 February 2026 - A new timetable will be introduced, all Cranbourne, Pakenham and Sunbury Line trains will run through the Metro Tunnel, and Frankston Line trains will return to the City Loop
Project delivery
VIDA Metro is responsible for planning and development of project reference design, site investigations, stakeholder engagement, planning approvals and procurement, through to the construction delivery and project commissioning phases.
Construction delivery
Works package | Procurement model | Delivery |
---|---|---|
Early works | Managing Contractor | John Holland |
Tunnel and stations | Availability based Public Private Partnership | Cross Yarra Partnership (CYP) consortium, comprising Lendlease Melbourne Metro, John Holland, Bouygues Construction, John Laing and Capella Capital. Metro Trains will provide technical, service and operational advice, as well as facilitate safe access to the rail corridor and manage disruptions to train services. |
Rail infrastructure | Competitive alliance | A consortium comprising John Holland, CPB Contractors and AECOM in partnership with Metro Tunnel Project and Metro Trains as the rail operator. From 2022, the remaining rail infrastructure works package will be delivered by a consortium called the Rail Network Alliance, comprising John Holland, CPB Contractors, Alstom, AECOM, Metro Tunnel Project and Metro Trains. |
Construction power | Utility Service Provider works | Beon Energy Solutions |
Rail systems | Competitive alliance | CPB Contractors and Alstom / Bombardier Transportation in partnership with Metro Tunnel Project and Metro Trains as the rail operator. From 2022, the remaining rail systems works package will be delivered by a consortium called the Rail Network Alliance, comprising John Holland, CPB Contractors, Alstom, AECOM, Metro Tunnel Project and Metro Trains. |
Tram infrastructure works | Franchise Works (Yarra Trams) | Yarra Trams |
Specialist advisors
- Aurecon Jacobs Mott MacDonald (AJM) Joint Venture (Technical, Planning and Engagement Advisor)
- KPMG (Commercial and Financial Advisor)
- Herbert Smith Freehills (Legal Advisor)
- Advisian (Constructability Advisor)
- Aquenta (Cost Advisor)
- O'Connor Marsden (Probity Advisor)