Construction Compound Plans

A Construction Compound Plan is a public document that outlines the operation of a site compound prior to its establishment.

The following covers Construction Compound Plans for Central Package, Early and Rail works. For all Eastern Freeway Package Construction Compound Plans, please refer to the Construction plans and reports page.

Boral Batch Plant Construction Compound Plan

A site compound will be established by Spark on Manningham Road, Manningham to support the Boral concrete batching plant. The Construction Compound Plan (PDF, 2.1 MB) was approved by the Executive Director, Planning Facilitation of the Department of Transport and Planning, under delegation from the Minister for Planning on 24 November 2023, prior to the compound works commencing.

Borlase Reserve Construction Compound Plan superseded by Lower Plenty Construction Compound Plan below

A site compound was established at Borlase Reserve, Yallambie. The Construction Compound Plan (PDF, 4.3 MB) was approved by the Minister for Planning on 11 May 2020 prior to the compound works commencing and variations were approved on 28 July 2021 and 8 November 2021. To find out more about these variations you can read the current approved Construction Compound Plan for Borlase Reserve (PDF, 18.8 MB), and the previous revision of the Construction Compound Plan for Borlase Reserve (PDF, 12.8 MB). This compound supported the Early Works scope and has been decommissioned.

Bulleen Motorway Control Centre Construction Compound Plan

A site compound was established by Spark on Bulleen Road, Bulleen. The compound supported workers involved in the construction of the Motorway Control Centre. The Construction Compound Plan was approved by the Manager Transport Projects (Acting) Infrastructure Assessment under delegation from the Minister for Planning on 11 August 2025 prior to the compound works commencing. Download the amended Construction Compound Plan (PDF, 1.7 MB). This compound supported the Early Works scope and has been decommissioned.

Bulleen Cut and Cover Construction Compound Plan

A site compound was established by Spark off Bulleen Road, Bulleen. The Construction Compound Plan (PDF, 3.2 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning) on 31 October 2022, prior to the compound works commencing. An amendment (PDF, 2.4 MB) was approved by the Deputy Secretary of the Department of Transport and Planning, under delegation from the Minister for Planning, on 22 February 2023.

A second amendment was approved by the Executive Director, Planning Facilitation under delegation from the then Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning) on 25 October 2023. Download the second amended Construction Compound Plan (PDF, 1.5 MB). This compound supported the Early Works scope and has been decommissioned.

Bulleen Civil, Structural and Roads Construction Compound Plan

A site compound will be established by Spark off Bulleen Road, Bulleen. The Construction Compound Plan (PDF, 3.1 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning) on 31 October 2022, prior to the compound works commencing. An amendment (PDF, 1.5 MB) was approved by Executive Director, Planning Facilitation of the Department of Transport and Planning, under delegation from the Minister for Planning on 31 May 2024.

Bulleen Park and Ride Site Compound Plan

A site compound was established at Thompsons Road, Bullen. The Site Compound Plan (PDF, 34.3 MB) was approved under delegation from the Minister for Planning, on 27 May 2022, prior to the compound works commencing. This compound supported the construction of the Bulleen Park and Ride, and has been decommissioned.

Church Road Construction Compound Plan

A site compound will be established at Church Road, Doncaster. The Construction Compound Plan (PDF, 28.7 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 29 January 2021 prior to the compound works commencing. This compound supported the Early Works scope and has been decommissioned.

Eastern Zone: WP9 Scope Site Compound Plan

A site compound was established at Carron Street, Balwyn North. The Site Compound Plan (PDF, 16.5 MB) was approved under delegation from the Minister for Planning, on 11 November 2021 prior to the compound works commencing, and amended on 7 December 2021 (PDF, 29.5 MB). This compound supported the Early Works scope and has been decommissioned. A new Construction Compound Plan (PDF, 12.8 MB) has been approved for a similar location to support the Eastern Freeway Construction works.

Frensham Reserve Construction Compound Plan

A site compound was previously established at Frensham Reserve, Watsonia. The Construction Compound Plan (PDF, 19.9 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 17 December 2020 prior to the compound works commencing. A new Construction Compound Plan was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 15 December 2021. To find out more, read the new Construction Compound Plan (PDF, 28.6 MB) for Frensham Reserve. This compound supported the Early Works scope and has been decommissioned.

Greenaway Street Construction Compound Plan superseded by Manningham Construction Compound Plan below

A site compound was established on Greenaway Street, Bulleen. The Construction Compound Plan (PDF, 2.4 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 17 July 2020 prior to the compound works commencing and amendments were approved on 28 July 2021 and 8 November 2021. To find out more about the amendment, read the updated Construction Compound Plan for Greenaway Street (PDF, 7.3 MB) and the previous amendment (PDF, 8.1 MB). This compound supported the Early Works scope and has been replaced by the Manningham Construction Compound.

Grimshaw Street Construction Compound Plan

A site compound will be established at Grimshaw Street, Greensborough. The Construction Compound Plan (PDF, 10.8 MB) was approved by the Deputy Secretary, Planning of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 14 April 2022 prior to the compound works commencing.

Jemena Zone Substation Construction Compound Plan

A site compound was established at Simpson Barracks. The Construction Compound Plan (PDF, 7.1 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 17 December 2020 prior to the compound works commencing and amendments were approved on 18 November 2021. To find out more about the amendment, read the updated Construction Compound Plan (PDF, 2.0 MB). This compound supported the Early Works scope and has been decommissioned.

Lenola Street Construction Compound Plan

A site compound will be established at Lenola Street, Macleod. The Construction Compound Plan (PDF, 8.4 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 17 December 2020 prior to the compound works commencing.

Lower Plenty Construction Compound Plan

A site compound was established by Spark at Borlase Reserve, Yallambie (formerly established as the Borlase Reserve compound by the Early Works Contractor CBP). The Construction Compound Plan (PDF, 2.0 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 3 August 2022 prior to the compound works commencing. This compound supported the Early Works scope and has been decommissioned.

Lower Plenty Structures Construction Compound Plan

A site compound will be established by Spark on Greensborough Road, Yallambie. The Construction Compound Plan (PDF, 1.7 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 5 October 2022 prior to the compound works commencing. An amendment was approved by the Deputy Secretary of the Department of Transport and Planning, under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning), on 3 August 2023. Download the amended Construction Compound Plan (PDF, 1.6 MB). A second amendment was approved by the Executive Director, Planning Facilitation, of the Department of Transport and Planning, under delegation from the Minister for Planning, on 11 December 2023. Download the amended Construction Compound Plan (PDF, 1.7 MB). A third amendment was approved by the Director, State Planning Facilitation, of the Department of Transport and Planning, under delegation from the Minister for Planning, on 9 August 2024. Download the amended Construction Compound Plan (PDF, 2.8 MB). A fourth amendment was approved by the Director, State Planning Facilitation, of the Department of Transport and Planning, under delegation from the Minister for Planning, on 16 September 2024. Downloaded the amended Construction Compound Plan (PDF, 2.2 MB). A fifth amendment was approved by the Director, State Planning Facilitation, of the Department of Transport and Planning, under delegation from the Minister for Planning, on 26 February 2026. Download the amended Construction Compound Plan (PDF, 1.6 MB).

Manningham Construction Compound Plan

A site compound will be established by Spark on Greenaway Street, Bulleen (formerly established as the Greenaway Street compound by the Early Works Contractor CBP). The Construction Compound Plan (PDF, 1.4 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 3 August 2022 prior to the compound works commencing.

Manningham North Construction Compound Plan

A site compound will be established by Spark on Manningham Road, Bulleen. The Construction Compound Plan (PDF, 22.4 MB) was approved by Executive Director, Planning Facilitation of the Department of Transport and Planning, under delegation from the Minister for Planning on 29 April 2024, prior to the compound works commencing.

Manningham SEM Construction Compound Plan

A site compound will be established by Spark off Greenaway Street, Bulleen. The Construction Compound Plan (PDF, 2.4 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning) on 31 October 2022, prior to the compound works commencing.

Manningham Structural M&E Construction Compound Plan

A site compound will be established by Spark on Bulleen Road, Bulleen. The Construction Compound Plan (PDF, 7.6 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 14 September 2022 prior to the compound works commencing.

Watsonia TBM Construction Compound Plan

A site compound will be established by Spark on Greensborough Road, Macleod. The Construction Compound Plan (PDF, 3.2 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Planning on 16 September 2022 prior to the compound works commencing. An amendment was approved by the Manager Transport Projects, Infrastructure Assessment, under delegation from the Minister for Planning, on 19 June 2025. Download the amended Construction Compound Plan (PDF, 1.8 MB).

Watsonia Vent Office Compound Stage 1 Construction Compound Plan

A site compound will be established by Spark on Greensborough Road, Yallambie. The Construction Compound Plan (PDF, 955.5 KB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning) on 31 October 2022, prior to the compound works commencing. An amendment was approved by the Deputy Secretary of the Department of Transport and Planning, under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning), on 3 August 2023. Download the amended Construction Compound Plan (PDF, 1.2 MB).

Watsonia Civil and Roads Compound Stage 1 Construction Compound Plan

A site compound will be established by Spark on Yallambie Road, Yallambie. The Construction Compound Plan (PDF, 1.6 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning) on 31 October 2022, prior to the compound works commencing.

Winsor Reserve Construction Compound Plan

A site compound, primary consisting of a Spoil Handling Facility, will be established by Spark at Winsor Reserve, on Greensborough Road, Macleod. The Construction Compound Plan (PDF, 5.7 MB) was approved by the Deputy Secretary of the Department of Environment, Land, Water and Planning under delegation from the Minister for Environment and Climate Action (acting jointly and severally with the Minister for Planning) on 17 October 2022, prior to the compound works commencing.