Test trains are running through the tunnels and on the Sunbury, Cranbourne and Pakenham lines between West Footscray and Hawksburn.
The rigorous testing program will continue in 2025 to ensure all the Metro Tunnel’s new infrastructure and systems are working together and are seamlessly integrated into the network.
That includes the platform screen doors and High Capacity Signalling (HCS) technology – both firsts for the Victorian rail network.
In mid-2024 testing shifted into a new phase that will involve repeatedly running all the systems and technology to ‘stress test’ it over many months.
When the first test trains entered the twin tunnels in July 2023 they were travelling at low speeds and being driven manually without using the tunnels’ high capacity signalling system.
Since then, test trains have moved to line speed of up to 80km/h, with 2 trains in each tunnel controlled by the high-tech signalling system.
The team has conducted hundreds of tests so far.
Trial Operations are underway on the Metro Tunnel. This is a ‘dress rehearsal’ for the project that involves running through a wide range of scenarios from opening and closing each of the five new underground stations, to major incidents so staff are prepared when the Metro Tunnel opens in 2025.
As part of trial operations, trains will run at times without passengers between Hawksburn and West Footscray through the Metro Tunnel using the new signalling system, with station staff and drivers.
Between 2020 and 2022, 2 X’Trapolis test trains were fitted with High Capacity Signalling. New trackside equipment was also installed. This testing allowed us to prove the new technology worked as expected with the existing signalling system.
Rigorous testing continued for over a year on a 4.5km section of track on the Mernda Line, between Epping and South Morang stations. Further testing on the Cranbourne, Pakenham and Sunbury lines followed.
Throughout 2022, we tested HCS and trains on the Cranbourne/Pakenham Line between Flinders Street and Westall. The new HCMTs were put through hundreds of different scenarios to ensure the HCS and the existing signalling system would work together.
Testing took place on the existing network during the first half of 2023, on weekends and overnight. Initial tests were between Flinders Street and Westall stations, before moving to between South Kensington to Tottenham stations.
The first test trains entered the Metro Tunnel in July 2023, kicking off rigorous testing of the signalling and other systems which continued into the first half 2024. This included: