Current works at Parkville Station

Major construction of the Metro Tunnel’s Parkville Station is complete.

This page outlines a snapshot of works happening in the area, details of impacts and working hours, and downloads of notifications sent to nearby residents and businesses. Sign up for enews to receive notifications to your inbox.

Current works

Smoke baffle installation works will take place on Grattan Street from September.

What we'll be doing

  • Establishing a temporary work site and at times setting up a 20-tonne crane on the northern Grattan Street footpath, in front of the University of Melbourne Medical Building, around the 2 easternmost station skylights
  • Installing smoke baffles on the concourse level at the main Grattan Street entrance
  • Removing materials using the crane via the station skylight –
  • Reinstating the skylight glazing and stonework and removing the work site in early November.

These works will have some impacts on footpath and pedestrian traffic. See the notice below for more information.